CLC urges inclusion of fluctuations provisions in contracts
Contents |
[edit] Introduction
On 7 July 2021, the Construction Leadership Council (CLC) called on those responsible for developing, agreeing and managing construction contracts to adopt fluctuations provisions to combat significant volatility in the market.
[edit] Recommendations
In an open letter to the industry, CLC co-chair Andy Mitchell said that following the challenges of COVID-19 in 2020/2021, the industry faced more obstacles in the form of the availability and pricing volatility of labour and materials.
He cited a range of factors coming together at the same time to present an "escalating challenge" to the sector, including: rising freight costs; a shortage of materials; a shortage of hauliers; transitioning from CE to UKCA marking with insufficient product testing capacity; and new EU-related immigration rules.
[edit] Time of transition
Mitchell said, "This volatility is likely to be something we must live with for a while to come and could have a significant impact on the time frames and delivery costs of many projects.
"Most forms of construction contract have standard provisions for managing volatility without the need to make contract amendments. These provisions, such as fluctuations provisions in JCT and NEC 4 Secondary X1, provide a means of collaboratively sharing the risks associated with this volatility. We have been fortunate enough to operate in a stable environment for a long time and these clauses have been seldom used. However, they are ideally suited to providing a means for managing the volatile period we are entering and therefore CLC strongly urge those responsible for developing, agreeing and managing contracts, existing and new, to consider adopting these provisions in their contracts."
He also noted that design changes were likely to be necessary as a result of product availability, creating contractual challenges in the process.
He added, "Again, the CLC would encourage a collaborative approach to be taken to managing these risks by considering actions such as allowing longer mobilisation and lead-in periods for contracts and including up-front ordering and payment to suppliers in order to secure manufacture and delivery slots for critical material resources.
"We know that we perform better as an industry when a collaborative and team-based approach is adopted. We also know that our industry is strong and is growing right now. We would therefore encourage you to consider this message and find ways to work together so that this growth opportunity is maximised, and a sustainable industry supply chain is maintained."
This article originally appeared on the CIAT website under the headline, 'CLC calls for adoption of fluctuations provisions in contracts'. It was published on 7 July 2021.
--CIAT
[edit] Related articles on Designing Buildings
- Alternative dispute resolution for construction ADR.
- CE marking in the construction industry.
- CIAT articles.
- CLC publishes guidance on COVID-19 impact for NEC4.
- Construction Leadership Council CLC.
- Extension of time EOT in construction contracts.
- Examining the 2021 construction materials shortage.
- Fluctuations in construction contracts.
- JCT.
- Materials shortage prompts extra planning,
- NEC 4.
- Onerous contract.
- Supply chains in construction.
- UKCA mark transition extension for construction products requested.
- What is causing the rise in steel prices?
[edit] External resources
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.